Construction Update

Construction Update

UPDATED December 10, 2012


The following offers a glimpse at forthcoming construction activities. Please remember that the commencement or completion of these activities is dependent upon weather and the discovery of any 'surprises' in the infrastructure. Thanks for your continued patience and support as we finish the trail.

CENTRAL CORRIDOR

From Alabama St. to West St. on the north side of Washington St. See map.

In 2012, the majority of construction activity will be the area between Capitol Avenue and West Street.  

CONSTRUCTION ACTIVITIES:

TRAFFIC RESTRICTIONS:

Anticipated completion dates: The hardscape between Alabama Street and Capitol Avenue was complete in December 2011. The hardscape between Capitol Ave. and West St. will be finished in December 2012 and plantings finished in November 2012.

On-site construction manager: Greg Broz, (317) 383-1196, gbroz@rwa.com

SOUTHEAST CORRIDOR

From Washington St. and Pennsylvania St. to Shelby and Prospect streets on Virginia Ave. See map.

In 2012, the majority of construction activity will be the area on Virginia Avenue between East Street and the interstate.

CONSTRUCTION ACTIVITIES:

On Tuesday, December 11, 2012, the contractor will close the ramp to northbound I-65/eastbound I-70 that is between the bridges on Virginia Avenue. This entrance ramp will still be accessible from Calvary Street. The closure is anticipated to last for two weeks. The contractor will be rebuilding some sidewalk, some street, a pavement joint, and upgrading curb ramps.

TRAFFIC RESTRICTIONS:

On Tuesday, December 11, 2012, the contractor will close the ramp to northbound I-65/eastbound I-70 that is between the bridges on Virginia Avenue. This entrance ramp will still be accessible from Calvary Street. The closure is anticipated to last for two weeks.

Traffic restrictions have been re-introduced on Virginia Avenue from East Street to the interstate creating two lanes of traffic in places where there is usually four lanes. This will continue throughout construction.

Anticipated completion dates: Hardscape of areas between Washington and East Streets, and between the Interstate and Prospect Street was complete in December 2011. Hardscape of the area between East Street and the Interstate and all landscaping should be complete in December 2012.

On-site construction manager: Brian Andres, (317) 407-3760, bandres@rwa.com

WEST CORRIDOR

From Indiana Ave. to White River State Park on the east side of Blackford Ave. See map. There is additional work on other parts of the completed trail that are included in this contract as well.

CONSTRUCTION ACTIVITIES:


TRAFFIC RESTRICTIONS:

There should be no traffic restrictions on Blackford Street due to Cultural Trail construction.

Anticipated completion dates: Work should be completed in November 2012.

On-site construction manager: Samer Butros, (317) 407-5543, sbutros@rwa.com