Construction of the Indianapolis Cultural Trail will be done in seven corridor stages over five years, beginning in 2007. The corridor schedule is subject to change.
What's Done So Far:
East Corridor Alabama Street — Began April 2007. Completed June 2008.
Northeast Corridor
North Street, New Jersey Street, Walnut Street, College Avenue and
Massachusetts Avenue to 10th Street (connecting to the Monon Trail). Began April 2009. Completed November 2010.
North Corridor
St. Clair Street, part of The Canal (between St. Clair and Walnut streets), Walnut Street, Meridian Street, American Legion Mall and North Street. Began July 2009. Completed June 2010.
Remaining Construction:
2010
Capitol & Alabama Corridor Capitol Avenue from Washington Street to South Street + Alabama St. from Market St. to Washington St.
2011
Southeast Corridor Alabama
Street, Washington Street, Pennsylvania Street, and Virginia Avenue
West Corridor The Canal, Indiana Avenue, Blackford Street, Washington Street and West Street
Central Corridor Market Street, Monument Circle, Illinois Street, Washington Street, Senate Avenue and Government Place
2012
Landscaping will be installed in the spring of 2012 on West and Central Corridors.
The entire eight-miles is scheduled to be completed by the end of 2012.